Bluewater Park Wellfield Assessment – Technical Memorandum Final
Basics
Title
Bluewater Park Wellfield Assessment - Technical Memorandum Final
Description
Technical memorandum summarizing hydrogeology assessment and review services for the Bluewater Park water system serviced by four bedrock wells, including Phase 2 well inspections and testing, and Phase 3 groundwater monitoring program results with analysis of declining wellfield productivity
Date
December 5, 2019
Creator Organization
EXP Services Inc.
Authors
Matthew D. Munn | Jay Rao
Document Type
technical manual
Document URL
Full Text URL
Subject Area
Data | Water Resources > Groundwater | Water Resources > Hydrology | Policy & Governance Data | Tools & Methods | Water Resources | Water-supply
Full Text
Document Information:
Date: December 5, 2019
Reference No.: VAN-00254172-A0
To: Steve Brubacher, P.Eng., Urban Systems Ltd.
Prepared By: Matthew D. Munn, M.Sc., P.Eng. and Jay Rao, M.A.Sc., P.Eng., CSAP
Project: Bluewater Park Wellfield Assessment, Mutiny Lane, Bowen Island, BC
Distribution: Glen Shkurhan, P.Eng., Interim Director of Engineering, Bowen Island Municipality
Total Pages: 9 + Attachments
1.0 INTRODUCTION
EXP Services Inc. (EXP) was retained by Bowen Island Municipality (BIM) to provide hydrogeology assessment and review services relating to the Bluewater Park water system, which is serviced by four bedrock wells. The scope of EXP's services was defined in consultation with Urban Systems Ltd. (Urban) personnel and BIM engineering staff. All work was completed in agreement with the authorized scope summarized in EXP's proposal to BIM (c/o Urban) dated June 24, 2019, which was the basis for BIM's Purchase Order #5752. EXP's scope of work was also incorporated into Urban's workplan separately delivered to BIM on June 18, 2019.
The primary objectives of EXP's 3-Phase workplan were to inspect, test and monitor the four Bluewater Park (BWP) wells for the purpose of characterizing on-going wellfield supply issues and identifying options for potentially increasing the overall wellfield productivity. A Phase 1 "Background Information Review" was completed in consultation with BIM and Urban staff and was the basis for finalizing the scope for the Phase 2 "Assessment of Existing Bedrock Wells #1 to #4". The Phase 2 scope was necessarily completed in two increments during the periods of July 22 to July 26, 2019 (Wells #1 and #4) and August 22-23, 2019 (Wells #2 and #3) and included the following tasks: Remove the existing BWP well pumps and inspect the physical condition; Complete downhole camera surveys to examine the physical condition of BWP well boreholes; Complete short-duration pumping tests to evaluate the relative productivity of the BWP wells; Install new "dip tubes" to allow installation of monitoring devices to measure water levels; and Establish a Groundwater Monitoring Program by installing automated dataloggers in the BWP wells to obtain a continuous record of groundwater levels during typical operating conditions.
The Phase 2 results for BWP Wells #1 and #4 were summarized in EXP's Technical Memorandum #1 delivered to BIM and Urban on July 28, 2019. The Phase 2 results for BWP Well #2 and Well #3 are included in this Technical Memorandum.
EXP's original Phase 3 scope included maintenance of a Groundwater Monitoring Program for two months during typical BWP wellfield operating conditions and an assessment of the productivity of a new Shallow Test Well, which was constructed in May 2019 at a location approximately mid-way between BWP Wells #2 and #4 and was completed within water-bearing sediments representing a potentially separate source of water for the BWP wellfield. However, in discussions with BIM engineering staff, the Shallow Test Well assessment was deferred until further notice.
This Technical Memorandum (Final) summarizes the results of all EXP work and provides related interpretations, comments and recommendations consistent with the content of an "Interim Summary" delivered to BIM and Urban on October 30, 2019. Use of this Technical Memorandum should include consideration of EXP's Technical Memorandum #1, the Section 5 Limitations and the attached "Interpretation & Use of Study and Report" (Attachment #1).
2.0 PHASE 2 – INITIAL ASSESSMENT OF BEDROCK WELLS
The Phase 2 program was executed by EXP field staff and a Certified Pump Installer (Precision Service and Pumps Ltd. [Precision]) with remote supervision from EXP's Senior Hydrogeologist during July and August 2019. The Phase 2 activities, observations and results are described in the following sections. Prior to commencing the Phase 2 work, the BWP wellfield pumps were turned off by BIM Operations Staff.
Upon completing the planned inspection and testing of BWP Well #1 and Well #4 during July 22 to 26, 2019, Precision was notified by BC Hydro that crane access to the remaining Wells #2 and #3 would not be allowed due to overhead powerline proximity. Accordingly, the Phase 2 inspection and testing of Wells #2 and #3 was delayed four weeks until a BC Hydro representative (i.e., Rokstad) determined how to execute the work according to WorkSafeBC requirements. During Precision's work in Wells #2 and #3 on August 22-23, 2019, Rokstad provided a dedicated witness tasked solely with watching Precision's activities to alert them if inadvertent line contact was imminent.
2.1 Pump Inspections
All downhole components (i.e., pump, motor, riser pipe and wiring) were removed from the four BWP wells for examination by Precision. Details of Precision's inspections are provided in the attached Pump Inspection Reports (Attachment #2).
All wells are currently equipped with Grundfos submersible pumps and 1 horsepower motors rated for 5 USgpm (US gallons per minute) maximum capacity. All pump/motor assemblies and all wiring were visually determined to be in "very good" condition and lacked evidence of damage or misuse. The plastic drop pipe in Wells #1, #3 and #4 were likewise observed to be in "very good" condition, but the galvanized metal drop pipe in Well #2 was observed to be highly corroded. The heights of all motor shafts were confirmed to be within the manufacturer's specified range and could be manually spun, which indicated the impellers were not obstructed. Wiring resistance-to-ground checks also verified the electrical function of the motors. Accordingly, no replacements parts (other than upgrading the Well #2 drop pipe to plastic) or repairs are referenced on the Pump Inspection Report forms.
2.2 Well Borehole Camera Surveys
A submersible side-viewing, focusable camera was lowered into the wells on July 23 (Well #1), July 24 (Well #4) and August 22 (Wells #2 and #3) to examine the condition of the bedrock boreholes. The surveys confirmed that all boreholes were unobstructed and open to the original drilled depths. A small-diameter PVC tube was observed in the Well #4 borehole, from approximately 170 ft-bg (51.8 m-bg) to the bottom of the borehole, which was likely inadvertently dropped into the well during previous maintenance work. Bedrock surfaces and fractures exposed along well borehole walls were observed to be unaffected by mineral accumulations or bio-fouling (e.g., slimes, filaments) that might restrict the movement of groundwater into the boreholes.
2.3 Short-Duration Pumping Tests (Preliminary Yields)
Upon completing the submersible camera surveys, the pump assemblies were reinstalled to the original depths. Independent short-duration pumping tests were then conducted using a constant pumping rate of 4.5 USgpm selected based on a maximum pump capacity of 5 USgpm. An inline flow meter and valve were temporary installed on each well riser pipe to allow monitoring and control of the applied pumping rate. Precision personnel intermittently obtained manual water level measurements during testing using a graduated electric tape. A graphical summary of the water levels acquired during testing is provided on Figure 1 (Attachment #3).
Well #1: Testing in Well #1 was completed on July 24, 2019. After 56 minutes of sustained pumping at 4.5 USgpm, the water level drawdown in Well #1 was approximately 108.6 ft (33.1 m) below the pre-test static (i.e., non-pumping) level of 243.0 ft-bg (74.0 m-bg). It was necessary to terminate the pumping test to avoid exposing the Well #1 pump and potentially damaging the motor. Based on the magnitude of the end-of-test drawdown, the applied pumping rate, and the initial static water level, the preliminary yield of Well #1 was estimated to be approximately 2.5 USgpm. For comparative purposes, the original yield of Well #1 was estimated at 10 USgpm to 12 USgpm in 1986.
Well #2: Testing in Well #2 was completed on August 23, 2019. After 44 minutes of sustained pumping at 4.5 USgpm, the water level drawdown in Well #2 was approximately 38.6 ft (11.7 m) below the pre-test static level of 240.5 ft-bg (73.3 m-bg); accordingly, it was necessary to terminate pumping to avoid exposing the pump and damaging the motor. Based on these results, the preliminary yield of Well #2 was estimated to be approximately 2.0 USgpm as compared to the original yield estimate of 15 USgpm to 20 USgpm in 1986.
Well #3: Testing in Well #3 was completed on August 23, 2019. After 120 minutes of sustained pumping at 3.8 USgpm, the drawdown in Well #3 was approximately 44.0 ft (13.4 m) below the pre-test level of 178.3 ft-bg (54.3 m-bg). Based on the measured drawdown, the applied pumping rate, and the initial static water level, the preliminary yield of Well #3 was estimated to be approximately 3.4 USgpm. For comparative purposes, the original yield of Well #3 was estimated at 8.0 USgpm in 1991. (Note: Pumping rate applied to Well #3 was subsequently determined to be 3.8 USgpm due to flow meter calibration error.)
Well #4: Testing in Well #4 was completed on July 25, 2019. After 120 minutes of sustained pumping at 4.5 USgpm, the drawdown in Well #4 was approximately 35.5 ft (10.8 m) below the pre-test water level of 292.8 ft-bg (89.2 m-bg). Based on the measured drawdown, the applied pumping rate, and the initial static water level, the preliminary yield of Well #4 was estimated to be approximately 9.4 USgpm. For comparative purposes, the original yield of Well #4 was estimated at 6.5 USgpm in 1991.
3.0 PHASE 3 – GROUNDWATER MONITORING PROGRAM
EXP field staff established the Phase 3 Groundwater Monitoring Program at the BWP wellfield on July 26, 2019, by installing pressure transducers with automated dataloggers in BWP bedrock Wells #1 and 4 and in two non-operating test wells (i.e., Shallow Test Well and Bedrock Test Well) constructed in May 2019 at locations between Well #2 and #4. Monitoring devices were subsequently installed in Wells #2 and #3 on August 23, 2019, after Precision completed the Phase 2 inspection/testing of these wells and installed new PVC tubes to accommodate the devices.
All monitoring devices were programmed to record water levels at a synchronized frequency of 5-minutes. Monitoring was maintained for two months until September 30, 2019, to collect water level information during typical operating conditions and also during a 10-day period of controlled sequential well operation. Data from the Shallow Test Well was further required to support an assessment of potential interactions between the deep bedrock aquifer that supplies water to the BWP wellfield and the near-surface groundwater system hosted by sediments overlying the bedrock aquifer.
The resulting 2-month record of BWP wellfield groundwater levels is summarized graphically on Figure 2 (Attachment #4). Data obtained during the period of July 26 to September 20, 2019, are representative of BIM's typical operation of the BWP wellfield, except during the two periods of Phase 2 inspection/testing. Figure 2 data during the 10-day period of September 20-30, 2019, are representative of a prescribed operational sequence comprised of alternating 24-hour intervals of zero withdrawals from the wellfield (to allow measurable aquifer recovery) followed by independent operation of each BWP well at the typical (i.e., default) pumping rate for 24 hours. Monitoring data for the September 20-30, 2019, period of controlled (i.e., sequenced) well operation are also summarized on Figure 3 (Attachment #5).
Well #1: The monitoring device installed in Well #1 was initially downloaded on August 14, 2019. Review of the preceding data confirmed the water level drawdown in Well #1 frequently exceeded the device installation depth of 331 ft-bg. Due to this unanticipated drawdown magnitude, the Well #1 transducer was replaced on August 15, 2019 with a device capable of recording the full range of water level variation. The replacement device was installed in Well #1 at the deepest practical position of approximately 365 ft-bg, near the top of the Well #1 pump. Routine operation of Well #1 (Figure 2) at approximately 4 USgpm caused water levels to rapidly decline and reduce the entire 128 ft column of water available for drawdown within approximately 2 hours of commencing pumping, followed by a on/off cycling on an approximately 2-hour frequency. This behavior was again observed during the late-September period of independent operation (Figure 3) and verifies that Well #1 was being over-pumped.
Well #2: Routine operation of Well #2 commenced on August 24, 2019 (Figure 2). The start-up pumping rate of approximately 4.7 USgpm (confirmed by BIM Operations staff) induced an extremely rapid consumption of the water column and the water level then remained relatively stable at approximately 284 ft-bg, which is equivalent to the Well #2 pump intake position. This condition was unchanged throughout both the routine operation period and controlled operation interval (Figure 3). This behaviour was anticipated based on BIM Operations staff's reported observations that Well #2 commonly pumps on a 30-second to 60-second cycle that alternates with non-pumping intervals of the same duration.
Well #3: Routine operation of Well #3 commenced on August 24, 2019 (Figure 2). The start-up pumping rate of approximately 3.1 USgpm (confirmed by BIM Operations staff) induced a maximum drawdown magnitude of approximately 30 ft (9 m) on September 9, 2019, which infers there was a residual (i.e., available) water column height of approximately 170 ft (52 m) above the Well #3 pump depth of 351 ft-bg. This limited water level drawdown response was also observed during the late-September controlled operation period (Figure 3).
Well #4: The monitoring device installed in Well #4 was initially downloaded on August 15, 2019. Review of the data for the period of July 26 to August 15, 2019, confirmed the water level drawdown in Well #4 was typically deeper than the device installation depth of 357 ft-bg. Due to this unanticipated drawdown magnitude, the Well #4 transducer was replaced with a device capable of recording the full range of water level variation. The replacement device was installed in Well #4 at the deepest practical position of approximately 425 ft-bg, near the top of the Well #4 pump. Controlled operation of Well #4 (Figure 3) with a start-up pumping rate of approximately 3.6 USgpm (confirmed by BIM Operations staff) induced a maximum drawdown magnitude of approximately 90 ft (27 m), which infers there was a residual (i.e., available) water column height of approximately 140 ft (42 m) above the Well #4 pump depth of 430 ft-bg. This limited water level drawdown response was also observed during the late-September controlled operation period (Figure 3).
Shallow Test Well: Monitoring of water levels in the Shallow Test Well confirms that groundwater levels within the surficial sediments overlying the bedrock aquifer were stable at approximately 12.0 ft-bg (3.6 m-bg) throughout the 2-month monitoring period. This generally indicates the shallow aquifer (i.e., water-bearing sediments) were not measurably influenced by groundwater withdrawals from the bedrock aquifer. This interpretation provides support for additional consideration of the Shallow Test Well as a potential supplementary source of groundwater for the BWP wellfield.
4.0 DISCUSSION
4.1 Declining Wellfield Productivity
The Phase 2 program confirmed that all BWP well pump assemblies are in good working condition and lacked evidence of damage or misuse that might reduce pump productivity. Inspection of the well boreholes (drilled into bedrock) further verified the wells were unaffected by mineral accumulations or bio-fouling that can impede groundwater entrance and reduce productivity. Absence of these physical or mechanical issues suggests that changes within the bedrock source aquifer are the most probable cause for the significantly reduced wellfield productivity reported in 2019. This interpretation is supported by measurement of aquifer water levels (depths) in the BWP wells on September 30, 2019, after 48 hours of zero wellfield withdrawals, which were 117.3 ft to 215.6 ft deeper than water depths measured at the time of well construction (Table 1).
Table 1. Non-Pumping Water Levels in BWP Wells shows: Well #1 (Feb. 1986) had 15.0 ft at time of construction and 227 ft on September 30, 2019, for a difference of -212.0 ft. Well #2 (Feb. 1986) had n/a at time of construction and 227 ft on September 30, 2019. Well #3 (Nov. 1991) had 17.7 ft at time of construction and 135 ft on September 30, 2019, for a difference of -117.3 ft. Well #4 (Nov. 1991) had 33.4 ft at time of construction and 249 ft on September 30, 2019, for a difference of -215.6 ft.
The Table 1 data indicate that non-pumping water levels in the BWP wells at the end of the 2-month Groundwater Monitoring Program were 117.3 ft to 215.6 ft (35.8 m to 65.7 m) deeper than levels at the time-of-construction, which is such a significant deepening of the static water level that it cannot be attributed solely to the single-season effects of high withdrawal volumes combined with seasonally low recharge. The magnitude of the water level change also cannot be attributed solely to groundwater withdrawals that occurred during the Summer 2019 monitoring period. Instead, the changes in aquifer static water levels are interpreted to represent a depletion of the aquifer water caused by an imbalance between the seasonal and/or annual rates of groundwater withdrawal and rates of natural aquifer recharge.
The Phase 3 monitoring program also confirms that during routine wellfield operation, water levels in all BWP wells are maintained at depths below water-bearing fractures that contribute groundwater to the wells. If the BWP wellfield groundwater levels do not appreciably recover during the 2019/20 winter months, it is very likely that some relatively shallower water-bearing bedrock fractures have either been partly or entirely dewatered and their contribution to the well(s) correspondingly diminished or eliminated. Allowing well water levels to frequently exceed the depth of a "major water-bearing fracture", as evident in the BWP monitoring data, is also not consistent with BC Provincial Government guidelines for sustainable well operation.
Although groundwater levels throughout the wellfield exhibited an overall increasing (i.e., recovery) trend both during and after the late-September controlled pumping period (Figure 3), the observed rate of increase was becoming progressively slower, which indicates aquifer water levels might only partly recover during the 2019/20 winter low-demand, higher-recharge conditions.
4.2 Bedrock Well Productivity
Short-duration pumping tests completed during the Phase 2 program were designed specifically to identify the BWP wells with the highest relative yield (i.e., productivity) by applying a common pumping rate to each well for a fixed time interval. On this basis, a comparison of the Figure 1 drawdown magnitudes generally confirms that the individual productivity (yields) of Well #3 and Well #4 exceed the productivity of both Well #1 and Well #2.
The Phase 3 sequential pumping of the BWP wells was a series of four consecutive 24-hour duration, constant-rate pumping tests completed in general conformance with the current BC Provincial Government "Guide to Conducting Pumping Tests". Accordingly, analysis of the Phase 3 pumping test data provides a higher-confidence estimate for the BWP well yields, as compared to the values estimated from the short-duration Phase 2 tests.
Combined analysis of the Phase 2 pumping test data trends (Figure 1) and the long-duration Phase 3 pumping tests (Figure 3) indicate that the individual yields of Well #1, Well #2 and Well #4 are 46% to 90% less than the values reported at the time of well construction, as summarized in Table 2. The Well #3 yield is relatively unchanged (Table 2).
Table 2. Summary of Bluewater Park Well Yield Estimates shows estimated yields in USgpm at time of construction compared to Summer 2019: Well #1 was 10-12 at construction, 2.5 in 2019, for a difference of -75% to -80%. Well #2 was 20 at construction, 2.0 in 2019, for a difference of -90%. Well #3 was 8 at construction, 7.5 in 2019, for a difference of -6%. Well #4 was 6.5 at construction, 3.0 in 2019, for a difference of -46%.
The Well #1 pump intake can be dropped an additional 34.0 ft (10.3 m) to the bottom of the well (Figure 3) to reduce the on/off cycling frequency; however, this may not increase the well yield due to the limited increase in available drawdown relative to the known rapid drawdown rate. Likewise, the Well #2 pump can be dropped an additional 21.0 ft (6.4 m) to the bottom of the well, but this modification may neither reduce the on/off cycling frequency nor increase the Well #2 yield, due to the resulting small increase in available drawdown.
Well #3 is currently operated at a start-up rate of approximately 3.1 USgpm, whereas the theoretical sustainable yield of Well #3 is 7.5 USgpm (Table 2), which equals the combined yield from the other three BWP wells. The available drawdown in Well #3 can be optimized by lowering the pump assembly to the lowest practical position of approximately 398 ft-bg (121.3 m-bg) and the existing pump replaced with a 10 USgpm capacity assembly. On this basis, Well #3 represents the best prospect amongst the existing BWP wells for potentially increasing the productivity of the BWP wellfield.
The theoretical yield of Well #4 is approximately 3.0 USgpm (Table 2), which is the second highest rated BWP well. Also, given the favourable drawdown trends and presence of a significant residual water column water after 24 hours of uninterrupted pumping (Figure 3), Well #4 is considered to be the best candidate "back up" well for Well #3, although not a full-capacity backup.
4.3 Additional Bedrock Wells
Drilling a new bedrock well(s) and/or deepening one or more of the existing BWP bedrock wells might provide additional groundwater to the BWP wellfield. However, there is potential for this to correspondingly increase the rate of aquifer water depletion, unless the new bedrock well(s) is positioned a minimum of approximately 700-1000 ft (200-300 m) from the BWP wellfield to reduce the probability of intersecting water-bearing fractures that are currently accessed by the existing BWP wells.
4.4 Supplementary Shallow Groundwater
Phase 3 monitoring of groundwater levels in the Shallow Test Well confirms the shallow water levels were uninfluenced by the BWP wellfield withdrawals. To further assess the viability of the shallow water-bearing sediments as a supplementary source of water for the BWP bedrock wells, an initial short-duration pumping test could be completed in the Shallow Test Well to obtain a preliminary estimate of the potential yield. Results from the initial hydraulic testing would be the basis for planning additional confirmatory testing.
5.0 CONCLUSIONS AND RECOMMENDATIONS
Based on the observations and results of EXP's Bluewater Park Wellfield Assessment, we offer the following opinions, interpretations and recommendations: Significantly deepened aquifer water levels within the BWP wellfield are caused by historical and on-going operation of the BWP wells at rates exceeding the natural aquifer recharge rate, which has correspondingly reduced the productivity of all BWP wells; Allowing well water depths to commonly exceed the depth of major water-bearing fractures has dewatered relatively shallow fractures that contribute less water to the BWP wells; Monitoring data for non-pumping periods indicate that aquifer water levels may not significantly recover during low-demand recovery periods (e.g., winter), which would confirm some shallow water-bearing fractures are permanently dewatered and full water level recovery not attainable; Continuous groundwater monitoring is recommended in one or more BWP wells to determine actual seasonal aquifer water level recovery during the winter-spring 2019/20 period; It is recommended the Shallow Test Well be preferentially considered as a supplementary groundwater source for the BWP wellfield. An initial short-duration pumping test could be completed to determine a preliminary estimate of the Test Well yield and to further assess the shallow water-bearing sediments as a sustainable water source; It is recommended that drilling of a new bedrock well be deferred until a Shallow Test Well feasibility assessment is completed. Any new bedrock well(s) should be positioned approximately 700-1000 ft (100-200 m) from the existing BWP wells; It is recommended an increased capacity pump be installed in Well #3 and the pumping assembly lowered to the deepest practical position in the well borehole. Well #3 and Well #4 have the highest theoretical yields and greatest available drawdown of the BWP wells; and Consideration should be given to suspending use of BWP Well #1 and Well #2 following the upgrading of Well #3 and confirmation of the hydraulic performance of the modified Well #3.
5.0 LIMITATIONS
This Technical Memorandum and attachments have been prepared by EXP Services Inc. for the exclusive use and consideration of Bowen Island Municipality and Urban Systems Ltd. and have been prepared in a manner consistent with the level of care and skill ordinarily exercised by members of the engineering and science professions currently practicing under similar conditions in the jurisdiction in which the services were provided. Opinions, interpretations and assessments provided in this Technical Memorandum are based on EXP's review and analysis of data referenced in this document.
Any use of this report for purposes other than the purposes described in the preceding sections and/or by any other party must first be verified in writing by EXP Services Inc. EXP does not accept any responsibility for damages resulting from other party's reliance on or use of the information, opinions, interpretations and conclusions contained in this report. The attached "Interpretation & Use of Study and Report" is an integral part of this technical memorandum and must be included with any copies of this document.
6.0 CLOSURE
We trust the information provided by this Technical Memorandum meets your current requirements. Should you have any questions regarding any aspect of this document, please contact the undersigned.
Submitted by: Matthew D. Munn, M.Sc., P.Eng., Senior Hydrogeologist, EXP Services Inc.
Reviewed by: Jay Rao, M.A.Sc., P.Eng., CSAP, Manager – Environmental Services Western Canada, EXP Services Inc.
Metadata
Keywords
wellfield assessment
|bedrock wells
|groundwater monitoring
|pumping tests
|water level drawdown
|well productivity
|hydrogeology
|aquifer depletion
|Bowen Island
|municipal water supply
Time Period
July 2019 to September 2019
Document ID
202510061845
Copyright holder
Not found
Document Filename
bwp_wellfield-study-me-2019-12-05_exp_202510061845.pdf
Storage Location
analysis/other_sources
Key Findings
The assessment found significantly reduced wellfield productivity with water levels 117 to 216 feet deeper than at time of well construction, indicating aquifer depletion from pumping rates exceeding natural recharge. Well yields have declined 46% to 90% since construction except for Well #3 which maintained its yield. Well #3 shows the highest theoretical yield at 7.5 USgpm and greatest potential for increased productivity. Shallow water-bearing sediments were unaffected by bedrock well withdrawals, suggesting potential as supplementary water source. Recommendations include upgrading Well #3 with increased capacity pump, continuing groundwater monitoring, assessing the Shallow Test Well, and considering suspension of Wells #1 and #2.
Methodology
Three-phase workplan including Phase 1 background information review, Phase 2 assessment involving pump removal and inspection, downhole camera surveys, short-duration pumping tests at 4.5 USgpm, and installation of monitoring dip tubes, and Phase 3 groundwater monitoring program with automated dataloggers recording water levels at 5-minute intervals for two months including a 10-day period of controlled sequential well operation
Graph Descriptions
Page 15: Figure 1 shows drawdown response monitoring from pumping tests in four Bluewater Park wells on July 24-25 and August 23, 2019, with semi-log plot displaying drawdown in feet versus time in minutes for each well, showing Well #1 had 108.6 ft drawdown after 56 minutes at 4.5 USgpm, Well #2 had 38.6 ft after 44 minutes at 4.5 USgpm, Well #3 had 44.0 ft after 120 minutes at 3.8 USgpm, and Well #4 had 35.5 ft after 120 minutes at 4.5 USgpm.
|Page 16: Figure 2 presents groundwater monitoring data from July 26 to September 30, 2019, showing water levels in feet below ground versus date for all four bedrock wells plus shallow and bedrock test wells, with data recorded at 5-minute intervals, displaying cycling patterns in Wells #1 and #2, stable deeper levels in Well #4, and periods of inspection/testing marked.
|Page 17: Figure 3 displays detailed 10-day cycled well operation from September 20-30, 2019, showing water level responses during alternating 24-hour pumping and recovery periods for each well independently, with annotations showing pump intake depths and available drawdown for each well.
Page Count
17
Publisher Location
Burnaby, BC
File Format
application/pdf
Geographic Locations
Bowen Island | Mutiny Lane | Bluewater Park | British Columbia | Canada
Street Address
Mutiny Lane, Bowen Island, BC | 275 - 3001 Wayburne Drive, Burnaby, BC, Canada V5G 4W3